From:

12155 Magnolia Avenue Unit 10-E,
Riverside, CA 92503

Phone: (951) 279-7705
Email: ema@imccleanup.com
CSLB Lic # 962294

Quote Number 0925
Quote Date November 27, 2019
Valid Until May 25, 2020
Total $62,658.25
To:
Kinney Construction Inc

830 W Fletcher Ave., Orange, CA 92865

1995 S. Standard Ave, Santa Ana ,CA

We hereby propose to furnish all equipment and materials, and perform the labor necessary for the completion of the following work

Hrs/Qty Service Rate/PriceAdjustSub Total
1 Demo walls on 395lnft
$6,240.000.00%$6,240.00
1 Demo ceiling tile, t-bar, insulation, electrical wire ect... on 1,835sqft
$1,835.000.00%$1,835.00
1 Demo restrooms floors, accessories, partitions, sinks, toilets
$1,500.000.00%$1,500.00
1 Demo all kitchen cabinets
$200.000.00%$200.00
1 Demo ceramic tile on 1,500sqft
$3,000.000.00%$3,000.00
1 Demo carpets on 60yrds
$150.000.00%$150.00
1 Demo 12 doors
$600.000.00%$600.00
1 Haul all debris off site includes dumpster fee
$1,100.000.00%$1,100.00
1 ALTERNATIVE to machine scrub and seal warehouse floor on 12,805sqft
$2,817.000.00%$2,817.00
1 ALTERNATIVE to grind to remove epoxy paint on 4,500sqft
$3,600.000.00%$3,600.00
1 ALTERNATIVE to grind and apply epoxy paint (chosen by costumer) on 12,805sqft $41,616.250.00%$41,616.25
Sub Total $62,658.25
Tax $0.00
Total $62,658.25