12155 Magnolia Avenue Unit 10-E,
Riverside, CA 92503
Phone: (951) 279-7705
Email: ema@imccleanup.com
CSLB Lic # 962294
Quote Number | 0253 |
Quote Date | November 8, 2018 |
Valid Until | May 7, 2019 |
Total | $12,123.00 |
3030 Walnut Ave, Long Beach CA
We hereby propose to furnish all equipment and materials, and perform the labor necessary for the completion of the following work:
Hrs/Qty | Service | Rate/Price | Adjust | Sub Total |
---|---|---|---|---|
1 | Polish 1st floor lobby on approx 1,600sqft Grind new concrete with a 30- or 40-grit metal-bonded diamond, Grind with an 80-grit metal-bonded diamond, Grind with a 150-grit metal-bonded diamond (or finer, if desired). Apply a chemical hardener to densify the concrete. Polish with a 100-grit or 200-grit resin-bond diamond, or a combination of the two. Polish with a 400-grit resin-bond diamond. Finish with a 800-grit resin-bond diamond. |
$6,800.00 | 0.00% | $6,800.00 |
1 | Machine scrub epoxy floor on 1st floor only on approx 14,580sqft |
$1,603.00 | 0.00% | $1,603.00 |
1 | Machine scrub concrete floor on 1st floor only on approx 2,400sqft |
$1,100.00 | 0.00% | $1,100.00 |
1 | Machine scrub on 1st floor in hallway |
$320.00 | 0.00% | $320.00 |
1 | Dust clean all A.C unites and wipe down walls in laboratory on 1st floor |
$1,850.00 | 0.00% | $1,850.00 |
1 | Wipe down walls in hallway on 1st floor only | $450.00 | 0.00% | $450.00 |
Sub Total | $12,123.00 |
Tax | $0.00 |