12155 Magnolia Avenue Unit 10-E,
Riverside, CA 92503
Phone: (951) 279-7705
Email: ema@imccleanup.com
CSLB Lic # 962294
Quote Number | 0713 |
Quote Date | August 7, 2019 |
Valid Until | February 3, 2020 |
Total | $194,571.00 |
342 N San Fernando Rd CA
3226 W Magnolia Blvd, Burbank CA 91505
We hereby propose to furnish all equipment and materials, and perform the labor necessary for
the completion of the following work
Hrs/Qty | Service | Rate/Price | Adjust | Sub Total |
---|---|---|---|---|
1 | Polish concrete floor on 7,500sqft on front sales floor |
$37,500.00 | 0.00% | $37,500.00 |
1 | Grind and seal rear production area on 1,500sqft |
$3,000.00 | 0.00% | $3,000.00 |
1 | Install 5,000sqft of drywall over existing plaster areas and new walls framed by Goodwill |
$15,000.00 | 0.00% | $15,000.00 |
1 | Lift rental fee for interior work |
$2,500.00 | 0.00% | $2,500.00 |
1 | Paint interior ceiling on 9,000sqft ( mask of all lights) |
$6,750.00 | 0.00% | $6,750.00 |
1 | Paint basement ceilings, restrooms, breakroom, janitor room, paint all walls in hallway, breakroom, restroom, janitor and storage room, paint new doors |
$3,665.00 | 0.00% | $3,665.00 |
1 | Pressure wash exterior wall on 10,000sqft, prep stucco throughout exterior wall and repair all damage areas, primer & paint 2 coats on walls, paint roof primer cap lime green on 400lf,/ paint blue on exterior walls on 200lf/ paint canopy fascia black on 150lf |
$17,000.00 | 0.00% | $17,000.00 |
1 | Boom lift rental fee for exterior work |
$2,500.00 | 0.00% | $2,500.00 |
1 | Demo all restrooms fixtures, accessories, partitions, 10lf of wall in breakroom, 1250sqft of plaster & drywall and haul into bin above parking,/ remove all abandoned plumbing pipes above restrooms, breakroom, & janitor ceilings/ remove 500sqft of VCT in breakroom, janitor and storage room/ remove all drywall around doors and opening to allow for framing rework |
$11,200.00 | 0.00% | $11,200.00 |
1 | Re-frame 3 doors opening to allow for new doors and frames, 3 opening leading to hallway,/ (repair 2 restroom area walls due to rotted studes approx 12pic) install backing for all accessories & fixtures |
$4,500.00 | 0.00% | $4,500.00 |
1 | Drywall and finishes on 1,250sqft of drywall in basement, restrooms, breakroom, janitor room, & storage room |
$6,250.00 | 0.00% | $6,250.00 |
1 | Install FRP in 2 restrooms and janitor room |
$2,688.00 | 0.00% | $2,688.00 |
1 | Safe off plumbing for demo, rework plumbing to provide waste line to breakroom sink, remove & cap 3 toilets rings, rework waste lines to 2 restrooms sink and utlility sink,/ repipe hot & cold water for water heater, 2 toilets, 2 restrooms sinks, 1 urinal, 1 breakroom sink Provide & reinstall (1) 40 gal electrical commercial water heater, (1) 2'' back floors device and re-rout water line to lower back flow device/ (1) ADA compliant breakroom sink with faucet, garbage disposal, supply lines/ (1) urinal and flush valve/ (2) ADA toilets with open front toilet seats and supply lines/ (2)complete sink in restrooms/ and (1) utity sink |
$25,320.00 | 0.00% | $25,320.00 |
1 | Provide and install door & frames (3) complete 3*7, paint grade doors with alum-atone timely frames |
$3,075.00 | 0.00% | $3,075.00 |
1 | Prep tile in restrooms to allow for epoxy, cement in abandoned toilet rings, epoxy with flakes in 2 restrooms and 1 breakroom |
$4,965.00 | 0.00% | $4,965.00 |
1 | Grind and seal approx 600sqft in basement |
$1,200.00 | 0.00% | $1,200.00 |
1 | Electrical safe off- rework electrical in basement restrooms, janitor room, breakroom, & storage/ provide (4) new circuits to breakroom/ run neutral to existing boxes/ add S switches to control lighting in basement area restrooms/ provide and reinstall approx 12 (4' strip lights) connect power to water heater |
$9,600.00 | 0.00% | $9,600.00 |
1 | Fire main back flow device |
$8,425.00 | 0.00% | $8,425.00 |
1 | Back flow device testing |
$425.00 | 0.00% | $425.00 |
1 | Millwork 9lf corion counter top with ADA laminate cabinet |
$5,200.00 | 0.00% | $5,200.00 |
1 | Final construction clean up |
$2,620.00 | 0.00% | $2,620.00 |
1 | Accessories fro restrooms (2) sets of grab bars |
$400.00 | 0.00% | $400.00 |
1 | Permits |
$2,600.00 | 0.00% | $2,600.00 |
1 | Permit process |
$500.00 | 0.00% | $500.00 |
1 | Tax fee | $17,688.00 | 0.00% | $17,688.00 |
Sub Total | $194,571.00 |
Tax | $0.00 |
Total | $194,571.00 |