From:

12155 Magnolia Avenue Unit 10-E,
Riverside, CA 92503

Phone: (951) 279-7705
Email: ema@imccleanup.com
CSLB Lic # 962294

Quote Number 0370
Quote Date January 28, 2019
Valid Until July 27, 2019
Total $11,543.32
To:
CMD Construction

9272 Jeronimo Road, Suite 102,
Irvine, CA 92618

7755 Center Ave, 6th floor Huntington Beach

We hereby propose to furnish all equipment and materials, and perform the labor necessary for the completion of the following work
Note: Does not include removing tile from Lobby
NOTE: If job is awarded we will need 6-8 weeks to complete and this price is for regular hrs work time and/or if its after hrs it will increase 50% of this contract</strong

Hrs/Qty Service Rate/PriceAdjustSub Total
1 Demo restrooms on 6th floor, all wall paper, tile walls, toilets, sinks, partitions, ceramic floors, counter tops and grind thin set in restrooms
$3,500.000.00%$3,500.00
1 Remove all paper off walls in hallways on 6th floor 3,348sqft
$5,220.000.00%$5,220.00
1 Demo carpet in hallway 134yrd
$835.000.00%$835.00
1 Remove glue from hallway 3,348sqft
$1,138.320.00%$1,138.32
1 Haul away all debris off site $850.000.00%$850.00
Sub Total $11,543.32
Tax $0.00
Total $11,543.32