12155 Magnolia Avenue Unit 10-E,
Riverside, CA 92503
Phone: (951) 279-7705
Email: ema@imccleanup.com
CSLB Lic # 962294
Quote Number | QUO-0029 |
Quote Date | April 5, 2018 |
Valid Until | October 2, 2018 |
Total | $302,797.50 |
240 North Orange Avenue Brea, CA 92821
Redlands
We hereby propose to furnish all equipment, materials, and perform the labor necessary for the completion of the following work:
Hrs/Qty | Service | Rate/Price | Adjust | Sub Total |
---|---|---|---|---|
451500 | Machine scrub and rinse and 1 coat of acrylic sealer 451,500 SF |
$0.07 | 0.00% | $31,605.00 |
200 | Epoxy coat Scrubber Dump (45 mil non skid color system 200 |
$8.00 | 0.00% | $1,600.00 |
2000 | Epoxy Coat White Sanitary Stripe with Three coat Primer/Epoxy/Uretahne System 2000LFx18”wide |
$8.05 | 0.00% | $16,100.00 |
600 | Epoxy coat Battery Charging Area 600SF (15x40 area) Price for ¼ Any additional square footage to be charge at $4.25/sq.ft |
$4.25 | 0.00% | $2,550.00 |
1 | Clean out and fill all slab control joints with Polyureathane material. Based on 53,700 LF Includes removal of existing MM80. ¼ “ x 1” joint fill |
$132,480.00 | 0.00% | $132,480.00 |
30000 | Clean out and fill all slab forklift wire joints with Polyereathane material. Based on 30,000 LF ¼ x ½ joint fill. Includes removal of MM80 to ½ depth |
$3.73 | 0.00% | $111,900.00 |
3750 | Misc epoxy patching- spalls from racks and old walls. Based on 3500 spalls, Cracks ¼ inch wider based on 250 LF NOTE: We will need 8-9 weeks to complete job starting from 4/18. |
$1.75 | 0.00% | $6,562.50 |
Sub Total | $302,797.50 |
Tax | $0.00 |
Total | $302,797.50 |