Quote Number | QUO-0096 |
Quote Date | June 5, 2018 |
Valid Until | December 3, 2018 |
Total | $188,605.00 |
2294 N Batavia Suite E,
Orange, ca
92865
(714) 921-9361
28545 Livingston Ave, Valencia, CA
We hereby propose to furnish all equipment and materials, and perform the labor necessary for the completion of the following work:
Hrs/Qty | Service | Rate/Price | Adjust | Sub Total |
---|---|---|---|---|
1 | Remove approx 360 LF. Of .walls and 13,000 sq. Ft. of carpet and 2,400 Sq.Ft. Of ceramic flooring at main office |
$16,420.00 | 0.00% | $16,420.00 |
1 | Remove 2 warehouse offices |
$10,025.00 | 0.00% | $10,025.00 |
1 | Remove North/South Demising wall (approx. 105 L.F.) |
$14,500.00 | 0.00% | $14,500.00 |
1 | Lift Rental |
$1,200.00 | 0.00% | $1,200.00 |
1 | Remove East/West Demising wall (approx. 170 L.F) |
$18,960.00 | 0.00% | $18,960.00 |
1 | Remove existing mezzaning and offices at warehouse |
$37,500.00 | 0.00% | $37,500.00 |
1 | Wallsaw, break and remove wall openings for 14 Truck Doors and champher inside and outside |
$40,000.00 | 0.00% | $40,000.00 |
1 | Remove section of wall, slab and soil for 14 new dock levelers (8'x6') |
$35,000.00 | 0.00% | $35,000.00 |
1 | Sawcut, break, and remove loading dock slab 12' x50' 6” below grade approx 12’’ thick | $15,000.00 | 0.00% | $15,000.00 |
Sub Total | $188,605.00 |
Tax | $0.00 |
Total | $188,605.00 |